Knowledge / AEC-native Data

Construction contracts (NEC, JCT, FIDIC)

The conditions of contract, particulars, amendments and schedules that define obligations, risk allocation, notices and payment between the parties.

The contract is where the project's risk is allocated, and it is the document most people avoid reading until something has gone wrong. Standard forms such as NEC, JCT, FIDIC and the Irish PW-CF suite arrive with the documents that change what the printed conditions mean: Z clauses and Contract Data in NEC, schedules of amendments in JCT, Particular Conditions in FIDIC, the Schedule in the public works forms. The obligations they create run through notices, deadlines and payment cycles that live in other documents. Structured knowledge makes the contract something a commercial team can question directly, with every answer traceable to the clause and the amendment that governs it.

What Teams Ask of the Data

  • What does this clause actually require once the amendments and particulars are applied?

  • Which notices do we have to give, to whom, by when, and what happens if we miss one?

  • Where has risk been moved from the standard form position, and in whose favour?

  • Which obligations flow down to the subcontract unchanged, and which have been altered?

  • What does the contract say about this event: a compensation event, a relevant event, a variation, or nothing?

  • Which documents take priority when the employer's requirements and the contractor's proposals disagree?

  • What did we agree to in the schedule of amendments that the site team has never seen?

What Generic AI Misses

Standard forms are widely available, so a general-purpose model has read them. That is the problem. Ask it about a clause and it will explain the unamended standard form, fluently and correctly, while your contract says something different in a Z clause or a schedule of amendments that the model has never seen. The answer is textbook accurate and contractually wrong.

The contract also does not work as a stand-alone text. Obligations depend on defined terms, on the particulars that fill in the blanks, on the order of precedence between documents, and on dates that only exist once the programme is agreed. A model reading the conditions alone cannot tell you whether a notice is late, because it does not know when the event occurred or what the contract data says the period is. It will produce a confident summary of a document that, as amended, does not say what the summary claims.

What Structured Knowledge Answers

QUESTION

If the utility connection is delayed by the statutory undertaker, what does our contract require us to do and by when?

ANSWER

This contract lists delay by a statutory undertaker as a compensation event, added by Z clause to the events in clause 60.1, and clause 61.3 puts the notification on the contractor. The Z clauses shorten the eight-week notification period in clause 61.3 to two weeks and make the early warning under clause 15 a condition precedent, which the unamended form does not do. They also require the quotation within one week of the Project Manager's instruction to quote, rather than the three weeks in clause 62.3. Clause 61.4 lets the Project Manager decline an event that arises from a fault of the contractor, so the answer flags the date of the contractor's application to the undertaker as the fact the event turns on.

SOURCES

conditions of contract, clauses 15, 60.1, 61.3, 61.4 and 62.3 as amended; Z clauses, items on notification periods and conditions precedent; contract data part one, completion date and periods.

Illustrative. The contract, amendments and periods are invented to show what an answer looks like; nothing here is a reading of a real contract or advice on one.

See it on your data.

See it on your data.

We onboard a focused slice of your project data, configure the ingestion paths, extract a structured context graph, and build a workflow against the resulting structured knowledge layer.

The Data in Context

The contract sits above the employer's requirements and the contractor's proposals and sets the order between them. It defines how variations and compensation events are raised and valued, and it is the document the tender pack was priced against. Contract obligation extraction and variation impact review both start from it.

Related Knowledge

Frequently Asked Questions

Frequently Asked Questions

Which contract forms does it work with?

Does it replace legal review?

Can it flag notice deadlines from the contract?